• Invert levels of inlet(s) sump and outlet pipe.
• Invert levels of any subsoil drains entering catchpit.
• True pipe lengths for catchpit leads, also pipe diameter, material, class, and grade.
• Siphon details (or as listed via drawing note that all constructed as per Regulatory Engineering
standard engineering detail drawing).
• Catchpit leads are to be shown up to the connection with the existing public Stormwater
system, and this connecting system must also be adequately identified and surveyed.
• Drainage RAMM sheets must be filled out for any alterations or additions to public roading
drainage. If you have not already received the template RAMM sheet for this asset type via
email, it can be obtained upon request from the Regulatory Engineer.
2.4.3. Retaining walls
• Location clearly identified with reference to names of adjacent properties or parks.
• Length of wall, foundation type, structure material and deck / rail material.
• Legal status (to be owned by whom).
• Building consent reference number.
2.4.4 Other required documentation
• RAMM sheets for roading assets are required for upload into the asset owner’s RAMM
database. These come as an electronic excel spreadsheet document with different sheets for
the different information required. The different sheets include a berm inventory, footpath
inventory, footpath surfacing, carriageway kerb & channel, carriageway inventory, shoulder
inventory, barrier fence rail inventory, carriageway surface, carriageway base, feature
inventory, minor structure, vehicle crossing, ads signs. For any particular job, some or all of
these sheets may be necessary.
• RAMM sheets will be forwarded with the template to any consent holders for which this asset
type is relevant. If you have not received your electronic copy of the RAMM sheets, please
contact your Development Engineer.
• Streetlights - Live data capture is required for streetlight as-built pick-up. This is to be carried
out by Auckland Transport’s nominated contractor at the developer’s cost. Streetlights must
also be identified on the as-built drawing with general specifications included (as a side note
if appropriate). Submission of documentation must be supported at