Page 1 of 37
March 2024
RE 2.1.23 (V3)
Regulatory Engineering
As-built requirements
Version 3 Published March 2024
Page 2 of 37
March 2024
RE 2.1.23 (V3)
Introduction
This document sets out the requirements for as-built documentation for any Auckland
Council public infrastructure works that create new assets or in some way alters the
existing assets of Auckland Council asset owners. In some cases, it is also appropriate
to apply these standards for private infrastructure assets constructed via and
engineering plan approval or resource consent.
These as-built plans and documents are required by Auckland Council to ensure that
the assets taken over meet engineering requirements, and that this information can then
be loaded into GIS systems and databases to ensure an up-to-date record of
infrastructure.
Structure
Auckland Council’s regulatory engineering department is part of the following
organisational delegation:
Auckland Council
Regulatory Service Directorate
Regulatory Engineering Department
Failure to comply
Auckland Council will not take on ownership and assets will remain private until the as-built
documentation has been received, checked, and approved. The acceptance of such
documentation is guided by the requirements set out in this document and engineering
practicability.
Page 3 of 37
March 2024
RE 2.1.23 (V3)
Document control provisions
Controlled document
Auckland Council (“the council”) as-built requirements is a controlled document with the
latest edition available free (pdf format) on our website. The council will always retain
the copyright for the as-built requirements and will retain the master copy.
The as-built requirements should always be used in conjunction with the relevant
Code of Practice (COP) and Quality Assurance Manual (QAM). It is the developer
and/or consultant’s responsibility to ensure that they are referring to the latest
edition of the as-built requirements, COP and QAM.
Document control amendments
The as-built requirements for Auckland Council is a “live” document and will be subject
to changes to maintain relevance to the council policies, developing best practices,
procedures and changing industry standards.
Please submit any proposed changes to the attention of the Regulatory Engineering
General Manager.
Page 4 of 37
March 2024
RE 2.1.23 (V3)
Key changes in this version
Version 3 of the Regulatory Engineering As-built requirements is being released to
incorporate changes to:
New Zealand Vertical Datum 2016 (NZVD 2016) will be replacing AUK1946 datum
from the 1
st of
July 2025. While we transition to NZVD 2016 both datums will be
accepted until 30 June 2024. From then any new Asbuilts submitted they must be
in NZVD2016.
Before 30
th
June 2024 you can use either NZVD 2016 or AUK1946 but you must
specify which datum you are using.
The As-built Certification section 3.2 and stamp has been updated to include
NZVD2016 and Certified Professional Engineering Surveyor as an acceptable
signature.
Sample Drawings have been updated.
Previous changes
As-built certification required on As-built drawings (3.2 page 12) and the schedule of
vested assets (appendix c) no longer requires private connection information.
From the 2
nd of
July 2018 the Engineering Plan Approval process will make sole use of
the Watercare Services Limited Compliance Statement process for all newly approved
Water and Wastewater assets to be vested. Following the approval of the assets under
the engineering approval, all construction observation and documentation reviews will
be undertaken by Watercare Services Limited in accordance with the Watercare
“Compliance statement policy Part 1 for land development and subdivision works
September 2017” and their asset recording standards.
Auckland Council Development Engineers will manage the asset acceptance processes
associated with stormwater, roading and park assets within the Engineering Plan
Approval, and will coordinate with Watercare engineers for the final issuance of the
Engineering Approval Completion Certificate.
Page 5 of 37
March 2024
RE 2.1.23 (V3)
Table of contents
Contents
Introduction ..................................................................................................................................... 2
Structure ......................................................................................................................................... 2
Failure to comply ............................................................................................................................. 2
Document control provisions ............................................................................................................ 3
Controlled document ................................................................................................................... 3
Key changes in this version ......................................................................................................... 4
Previous changes ........................................................................................................................ 4
Table of contents ............................................................................................................................. 5
1.
Engineering Approvals - background ...................................................................................... 7
1.1. Public works ..................................................................................................................... 7
1.2. Asset owners .................................................................................................................... 7
1.3. Asset ownership roles diagram ......................................................................................... 8
1.4. Scope of works ................................................................................................................. 8
2.
The as-built process ................................................................................................................ 9
2.1. General ............................................................................................................................. 9
2.2. Processing times ............................................................................................................. 10
2.3. Completing a stormwater as-built .................................................................................... 10
2.5. Completing a streetscape (Parks) as-built ....................................................................... 16
3.
Required Documentation ....................................................................................................... 18
3.1. Engineering completion certificate ................................................................................... 18
3.2. As-built certification ......................................................................................................... 18
3.3. Schedule of vested assets .............................................................................................. 19
4.
Vesting of infrastructure ......................................................................................................... 20
5.
Post completion audit............................................................................................................. 21
6.
Appendices below. ................................................................................................................ 21
Appendices:
Appendix A Statement of Certification: Engineering Approval template
Appendix B Sample statement of certification: Engineering Approval
Appendix C Schedule of Vested Assets (SVA) template
Appendix D Sample Schedule of Vested Assets
Appendix E Schedule of Abandoned Assets (SAA) template
Page 6 of 37
March 2024
RE 2.1.23 (V3)
Appendix F Sample Schedule of Abandoned Assets (SAA)
Appendix G Sample stormwater drainage as-built
Appendix H Sample re-lay as-built
Appendix I Sample roading as-built
Appendix J Sample pond as-built
Appendix K Sample wetland as-built
Appendix L Sample Engineering Approval Completion Certificate
Page 7 of 37
March 2024
RE 2.1.23 (V3)
1.
Engineering Approvals - background
1.1. Public works
Engineering Approvals are issued predominantly for any changes or additions to public
infrastructure in the Auckland region. This infrastructure includes wastewater and
stormwater drainage, water supply, roading, street trees, street furniture, and other
miscellaneous asset types.
1.2. Asset owners
Assets to be vested to Auckland Council as public infrastructure will eventually become
the property of one of five asset ownership bodies within or outside council. These asset
owners are:
Watercare Services Limited (Watercare)
Healthy Waters - Infrastructure and Environmental Services
Auckland Transport
Community Facilities
Property
These bodies have defined responsibilities in terms of asset ownership. Auckland Council
(the consenting authority) acts on their behalf to manage the approval process to ensure
the integrity of the new assets as a pre-requisite before the respective groups accept
ownership. Auckland Council undertakes compliance activities and as-built reviews for
these assets, except in the case of water and wastewater infrastructure which from the
2
nd
of July 2018 will be managed by Watercare directly but still within the Engineering
Approval process.
In this capacity, the council requires as-built documentation and performs checks to the
satisfaction of all internal Council departments and Auckland Transport. Projects of
significant scale and / or of perceived risk may also include direct involvement with those
asset owners.
Page 8 of 37
March 2024
RE 2.1.23 (V3)
1.3. Asset ownership roles diagram
Regulatory Engineering
Watercare
Services Limited
Healthy Waters
Dept
Auckland
Transport
Community
Facilities Dept
WW infrastructure
SW infrastructure
Roads
Street trees
WW pipes
SW pipes
Footpaths
Street gardens
WW manholes
SW manholes
Kerb & channel
Formed planters
WW pump stations
SW outlets
Road marking
Grass berms
Watermains
SW inlets
Pram crossings
Public paved areas
Non-potable water
Treatment devices
Street lights
Bus shelters
Fire hydrants
Ponds
Road drainage
Litter bins
Sluice valves
Dams
Road signs
Fountains
Peet valves
Traffic lights
Seats / benches
Public artwork
Note: Asset types above not limited to i.e. examples only
1.4. Scope of works
This guide is designed for the majority of private development works in the Auckland region.
These tend to consist of subdivisions of existing sites and commercial redevelopments. For
major development projects that will have a transformative effect on the local infrastructure
networks, direct contact with the consenting authority and asset owners may be required
throughout the entire consent process.
Asset Owners
Page 9 of 37
March 2024
RE 2.1.23 (V3)
2.
The as-built process
2.1. General
To enable efficient processing of the as built and completion of the Engineering Approval, the
following is required:
1.
Submit as-built to the Regulatory Engineer in .pdf (vectorised i.e. not scanned), and dwg
or .dxf format. Contact details can be found in your letter of Engineering Plan Approval.
The subject line should show address and engineering approval number, for example:
150 Great South Road, Manukau ENG60311000. Once the as-built has been approved,
an electronic copy of the certification form, Schedule of Vested Assets and (if required)
Road Asset Maintenance Management (RAMM) data templates and Schedule of
Abandoned Assets will be forwarded for completion. Section 3 provides details as to how
these documents are to be completed. The schedule must reflect true pipe lengths and
number of manholes as denoted on the final accepted as-built. Any copies of asset
owner’s confirmations should be provided.
2.
A CCTV of all new public stormwater drainage will be required where the full extent of the
pipes to be vested as public must be surveyed. This should be submitted to the council
for review along with the accompanying log sheets and letter from suitable qualified
professions comments on the findings of the CCTV.
3.
A Development Engineer will advise if further requirements are needed, including final
inspection. Please only reply via email to maintain a clear correspondence trail and enable
Council to process your as-built as quickly as possible.
4.
Once the as-built data has been checked and approved by Auckland Council the signed
pdf copy is to be sent by email to the Regulatory Engineer.
5.
Final inspection of works will be required after steps one to four have been completed.
Asset owners are to be invited to the inspection.
6.
On acceptance of public infrastructure works by Council, an Engineering Approval
Completion Certificate will be sent to the applicant’s engineer.
NB: For Water and Wastewater assets covered by the Engineering Approval, please refer to
Watercare as-built requirements. Regulatory Engineering will receive the finalised as-built plans,
schedule of assets and Watercare Certificate of Acceptance.
Page 10 of 37
March 2024
RE 2.1.23 (V3)
Note specific drawing requirements are covered under Sections 2.1 to 2.3.
2.2. Processing times
For Regulatory Engineering to process your as-built documentation promptly, we will endeavor to
assess within 10 working days, depending on the accuracy and completion of information. Please
submit as-built plans to your Regulatory Engineer as soon as possible following the completion
of physical works.
Any errors identified on the as-built plans will require a revised plan to be provided for
reassessment.
2.3. Completing a stormwater as-built
2.3.1. The as-built
Stormwater As-built Plans must show the following:
Co-ordinates to be in New Zealand Transverse Mercator (NZTM) for all assets shown in the
electronic file and on the signed paper copies. For examples refer to the sample drawings in
Appendices D, E, F, I and J. Accuracy is to be to 0.05m.
North point.
Property boundaries, street names and numbers.
Property address and engineering approval number.
Any assets related to or affected by the project clearly detailed and labelled as new / existing,
public / private, clearly denoting all assets that are to be taken over as public. Note to include
at least the first connecting manhole, pipe etc.
All affected pipe inlet levels and outlet levels (including existing assets); levels to be in
orthometric heights related to Auckland 1946 Height Datum accuracy (local) to 0.01m or
New Zealand Vertical Datum (NZVD2016) and from 30
TH
June 2024 NZVD only.
All material types and sizes of new assets (e.g.; 1050 precast concrete manhole/ 225 RCRRJ
/ Class x).
Pipe grade (in percentage).
Status of any pipes removed, abandoned or grout filled.
True pipe length (not MH center to MH center).
Flow directions.
Page 11 of 37
March 2024
RE 2.1.23 (V3)
Dimensions from boundaries to private service connections.
If a drop manhole has been constructed, a section will be required giving all invert levels.
All pipe protection measures, e.g. concrete capping.
Company logo, address and contact details of persons completing the as-built.
Certification panel - refer section 3.2.
All revisions are to be clear on the drawing and a table provided on the drawing block. Revision
dates must be included.
The code of drawing colours to be used are as follows:
Stormwater: Green
Removals and abandonments: Orange
Combined stormwater and wastewater: Magenta
Wastewater: Red
Watermain: Blue
Non-potable water: Purple
2.3.2. Stormwater inlet / outlet details
Co-ordinates at the point of the inlet / outlet pipe.
Inlet / outlet pipe invert level.
Outlet or inlet structure details, e.g. concrete apron, rip rap constructed with 150mm rock spall
etc. In general, the approved consent drawings give a good outline of the detail required for
the inlet /outlet structures and associated works.
The receiving and contributing environment must be detailed, and if not surveyed at least
generally identified and named e.g. Wiri Stream.
Where natural water bodies are concerned, it is helpful to reference the outfall structures in
relation to ten-year flood levels and flood prone areas as identified on council GIS.
Any existing regional stormwater discharge consents associated with the works must be
transferred to Auckland Council at the time of lodging the as-built. Upon vesting, Auckland
Council will take ownership of the associated responsibilities (Refer Application form “Notice
of Transfer of a Resource Consent to Another Person” in appendices).
Page 12 of 37
March 2024
RE 2.1.23 (V3)
2.3.3. Ponds, wetlands, and treatment devices
Stormwater Ponds and treatment devices shall be identified on the plan as follows:
Coordinates provided for the outline.
All inlets, outlets, orifices, risers, trash rack device (e.g. scruffy dome) and their dimensions
and material types etc.
A long section and cross section showing the water level control device, and various storage
levels, i.e. WQS, specific AEP levels and dead water level.
A long section and sufficient cross sections to show the general profile and features of the
pond or wetland and a long and cross-section of the spillway.
The length, width, and depth of the pond area sufficient as to confirm design volumes.
Any erosion control measures at inflow and outflow
Completion report with notes and measurements confirming any special design features and
on-site clean-up and disposal. Statement on seeding and fencing and safety and access
features. Must be signed and dated including statement that the feature meets or exceeds the
approved design.
A certification panel as shown in the sample drawings.
Clearly show access tracks and safety aspects such as fencing, handrails, benching:
o As generally shown in the sample drawings provided in Appendices J & K.
2.3.4. Re-lays
Re-lays of existing public stormwater do not require a surveyed as-built. In its place a drafted
plan, produced by the registered drainlayer who carried out the works and submitted with the
original consented plan as a reference meets requirements.
As with any other as-built, a completed statement of certification from the engineer overseeing
the works, a schedule of vested assets, a post construction CCTV, and verification of
completed inspections (carried out by a Development Engineer, not a Building Inspector) are
all required for acceptance of the infrastructure.
As with a standard drainage as-built, pipe lengths, diameter, material, and class must be
given, along with address, engineering consent number, and site locality.
Connection details to the existing pipes / system must also be given.
Page 13 of 37
March 2024
RE 2.1.23 (V3)
The re-lay must be located with distances from known fixed points e.g. boundaries and/or
manholes.
Further to this it must be clear from the as-built which section of public drainage pipe it is that
has been replaced i.e. adjacent public manholes named as per GIS description or any other
means which makes the infrastructure affected clear.
Page 14 of 37
March 2024
RE 2.1.23 (V3)
2.4. Completing roading as-builts
2.4.1. The as-built
Roading as-built plans, certificates, Road Asset Maintenance Management (RAMM) and other
forms are required for all new Roading infrastructure to be vested in Council. Regulatory
Engineering will forward the documentation to Auckland Transport (AT) for review. Note AT will
require a minimum of 5 working days to check information provided.
On acceptance Regulatory Engineering will issue the Engineering Approval Completion
Certificate. A final joint inspection with AT assets representative and Regulatory Engineer will be
required.
Roading as-built plans must comply with the general requirements set out for a drainage as-built
in that it must: have the electronic file set in and show all assets in terms of NZTM; property
boundaries, street names, numbers, and locality must be identified; address and consent number
must be stated on the as-built. In addition to this, a roading as-built must show the following:
The extent of the works carried out under the consent must be clearly denoted, with any public
/ private boundaries clearly defined.
The roading as-built must show as surveyed; new roads, kerb lines, footpaths, streetlighting,
road drainage with catchpit leads, road signs, road marking, traffic signals, pram crossings,
bus shelters, other associated street furniture and any retaining walls located within the road
reserve and to be vested with council.
Kerb lines on curves to be surveyed at 5m intervals and show coordinates.
Company logo, address and contact details of persons completing the as-built.
Certification panel.
All revisions are to be clear and obvious on the drawing and in the revisions table of the
drawing title block.
2.4.2. Catchpit details
Centre co-ordinates for catchpit grates (in NZTM)
Catchpit dimensions
Page 15 of 37
March 2024
RE 2.1.23 (V3)
Invert levels of inlet(s) sump and outlet pipe.
Invert levels of any subsoil drains entering catchpit.
True pipe lengths for catchpit leads, also pipe diameter, material, class, and grade.
Siphon details (or as listed via drawing note that all constructed as per Regulatory Engineering
standard engineering detail drawing).
Catchpit leads are to be shown up to the connection with the existing public Stormwater
system, and this connecting system must also be adequately identified and surveyed.
Drainage RAMM sheets must be filled out for any alterations or additions to public roading
drainage. If you have not already received the template RAMM sheet for this asset type via
email, it can be obtained upon request from the Regulatory Engineer.
2.4.3. Retaining walls
Location clearly identified with reference to names of adjacent properties or parks.
Length of wall, foundation type, structure material and deck / rail material.
Legal status (to be owned by whom).
Building consent reference number.
2.4.4 Other required documentation
RAMM sheets for roading assets are required for upload into the asset owner’s RAMM
database. These come as an electronic excel spreadsheet document with different sheets for
the different information required. The different sheets include a berm inventory, footpath
inventory, footpath surfacing, carriageway kerb & channel, carriageway inventory, shoulder
inventory, barrier fence rail inventory, carriageway surface, carriageway base, feature
inventory, minor structure, vehicle crossing, ads signs. For any particular job, some or all of
these sheets may be necessary.
RAMM sheets will be forwarded with the template to any consent holders for which this asset
type is relevant. If you have not received your electronic copy of the RAMM sheets, please
contact your Development Engineer.
Streetlights - Live data capture is required for streetlight as-built pick-up. This is to be carried
out by Auckland Transport’s nominated contractor at the developer’s cost. Streetlights must
also be identified on the as-built drawing with general specifications included (as a side note
if appropriate). Submission of documentation must be supported at
Page 16 of 37
March 2024
RE 2.1.23 (V3)
that time by a producer statement completed by the lighting manufacturer and installer. The
following is required:
Approved Street Lighting Design and a certified pdf as-built plan showing street light
position
Sign off from the Design Engineer that the installation has been built in accordance
with the approved design.
The Electrical Safety Certificate, Record of Inspection and Certificates of
Compliance for individual Street Lights.
The RAMM data for the streetlights.
Certificate of Completion and record of Inspection for the electrical work from
Network Contractor: e.g.-Vector/North power.
Road signs - Live data capture is required for road sign as-built pick-up. This is to be carried
out by Auckland Transport’s nominated contractor, at the developer’s cost. Road sign
locations must also be identified on the as-built drawing.
Traffic lights - The client must contract one of the known traffic light installation companies
within the Auckland region to carry out these works. These companies have the expertise to
complete the as-built documentation process and submit the details to the Traffic
Management Unit (TMU), a separate body, for upload into their systems. Upon acceptance of
this data, the contracted company will supply you with a copy of the accepted data, which
must be provided to Regulatory Engineering, which will in turn be stored by Auckland
Transport in their document registry. In addition to this a producer statement must also be
provided for the traffic light infrastructure.
2.5. Completing a streetscape (Parks) as-built
2.5.1. The as-built
Streetscape as-built documents have different requirements from the other asset types. Parks
asset types may have different as-built requirements depending on the asset type. If you are
uncertain what may be required of you, please contact your Development Engineer (Assets), who
may forward your query on to Parks for specific / uncommon asset types.
Street trees are the most common asset type to be vested with Auckland Council Parks. They
must fulfil the requirements as following:
Upon application to Regulatory Engineering, a CSV file will be provided that must be completed
by the applicant giving details about the street trees. This is essentially a spreadsheet format
Page 17 of 37
March 2024
RE 2.1.23 (V3)
and will include information such as co-ordinates of the assets, tree type and age, and potentially
other information fields. Upon request of the file format, you will be put in direct contact with a
representative of Parks who will assess the information that will be necessary for that instance
and will provide guidance as to how to complete the documentation correctly.
Street furniture is also a common asset type that may be vested. Again, you will be provided with
the appropriate CSV file and contacts within Parks to ensure that you can complete the
documentation as required.
2.5.2. Supporting documentation
The Engineering Approval issued for these works will be explicit in outlining the requirements
to be met throughout the course of the works. These include site and nursery inspections to
be carried out by Parks Inspectors.
To satisfy Regulatory Engineering, the conditions of the consent must be shown to have been
met and complied with throughout. Full written sign-off for the completion of the works is
required from the City Parks Services representative who has been assigned to this project.
This is to be forwarded to your Development Engineer.
Activity reports are generally required for sign-off of landscaping / street trees. The full set of
these reports must be submitted to your Development Engineer along with the completed As-
built drawing and sign-off from Parks.
A schedule of vested assets is still required for this asset type, however a Statement of
Certification: Engineering Approval is not appropriate. Sign-off is instead required from the
landscape architect, stating that the completed works adhere to the agreed design and
methodology.
Page 18 of 37
March 2024
RE 2.1.23 (V3)
3.
Required Documentation
3.1. Engineering completion certificate
When Regulatory Engineering is satisfied that all as-built documentation has been
accepted and the public works have been approved, the consent file will be sent for final
invoicing. The applicant as listed on the original Engineering Approval application form
will be sent the final invoice, and upon payment, an engineering approval completion
certificate (EACC) will be issued. This document is what may be required to support
application for 224c certificate or building code compliance certificate.
An example of a final engineering completion certificate is found in Appendix L - Sample
engineering approval completion certificate.
3.2. As-built certification
Final copies of the as-built plan must include a signed certification statement by the
Registered Professional Surveyor, Licensed Cadastral Surveyor or Certified Professional
Engineering Surveyor responsible for the as- built, in the following manner:
I certify that these As-built Plans are an accurate record of the works undertaken and that:
The Coordinates (X, Y) are in terms of NZTM on NZGD (2000), and are within
50mm.
The Levels (Z) are in terms of the NZVD 2016 / Auckland 1946 (MSL) LINZ datum
(DOSLI datum), and are within the following tolerances:
- For all pipe inverts & roadside channels to be within +/- 10mm (local circuit i.e.
internal/relative consistency required only)
- For all other assets +/-20mm (e.g. Manhole covers, Earthworks)
Name:
Signed:
Registered Professional Surveyor / Licensed Cadastral Surveyor/
Certified Professional Engineering Surveyor
Registration Number:
Date:
Contact Phone:
Email:
Page 19 of 37
March 2024
RE 2.1.23 (V3)
Regulatory Engineering acceptance of the as-built plans does not absolve the certifier of
ongoing responsibility for the information provided nor does it absolve the certifier of any
other approvals that may be required by Watercare Services Limited, Auckland Transport,
Parks, or other bodies.
An example of a completed as-built certification panel is found in Appendix G - Sample
Drainage As-built.
3.3. Schedule of vested assets
3.3.1. Function
The schedule of vested assets itemises the costs for the respective elements of the
development. Auckland Council is required by law to apportion a value to its assets that
reflects the true installation cost. In the case of assets created under engineering
approvals, this value is provided by the developer or their agent and must exclude
consenting fees and any consultant or project management fees.
3.3.2. Completing the form
The schedule of vested assets form is to be signed by the agent or developer and must
break down itemised assets (for example, cost of wastewater pipes, manholes, fire
hydrants etc). All pipe lengths and number of installed assets must be in accord with the
final approved as-built. All fields in the bottom section of the form must be filled out i.e.
name, company, position along with signing and dating the form.
An example of a completed schedule of vested assets is found in Appendix D - Sample
Schedule of Vested Assets.
Page 20 of 37
March 2024
RE 2.1.23 (V3)
4.
Vesting of infrastructure
Following final acceptance of the assets and issuance of the engineering approval
completion certificate, Regulatory Engineering carry out certain processes in order to vest
the infrastructure as an Auckland Council public asset. The main component of this is the
release of a project completion documentation for each job. These documents summarise
necessary information accepted though the as-built process, and formats them for release
to the respective asset owners. On the rare occasion it is found at this point that necessary
details may have been overlooked during the checking process and are now required to
be submitted for completion of this document. Regulatory Engineering may contact the
project engineer / surveyor at this point for further details in order to complete this
document.
In conjunction with the internal release of the completion documents, the .dwg / .dxf
drawing file submitted through the as-built process will be distributed to Auckland Council
GIS for uploading onto the public system. From this point on the public assets formally
vested will now be visible to Auckland Council residents and ratepayers and can be
utilised for further development.
Page 21 of 37
March 2024
RE 2.1.23 (V3)
5.
Post completion audit
Once vesting has been completed, a post completion audit may be carried out.
The respective asset owner, upon receipt of the assets through the vesting process, may
carry out post completion audits to verify that the new assets meet minimum standards.
If deficiencies are found, then they may defer ownership and request Regulatory
Engineering to contact the client for remediation. In this capacity Regulatory Engineering
carry out further investigations to resolve issues and satisfy all parties. The point of
contact for this process is primarily the certifying chartered professional engineer /
registered professional surveyor who has signed their name to the Statement of
Certification.
6.
Appendices below.
Page 22 of 37
March 2024
RE 2.1.23 (V3)
Statement of Certification:
Engineering Approval
I,
of
(Company name)
being a Chartered Professional Engineer under the provisions of the Chartered Professional Engineer Act
2002 or Registered Professional Surveyor (New Zealand Institute of Surveyors), have personally or
through personnel under my control carried out periodic reviews of the following works, and based upon
these reviews and information supplied by the Contractor during the course of those works hereby certify
that all engineering works;
shown on As-built plans:
prepared by
In accordance with the approved Engineering Plans, number: ________________________
at address
Lot #
DP #
have been constructed in accordance with sound and accepted engineering principles, the manufacturers
recommendations and comply with all provisions of the Unitary Plan, relevant Auckland Council
Engineering Standards, and the specific requirements of the Development Consent(s) and Engineering
Approval (and approved amendments), including completion and other tests.
I understand that by signing this statement of certification I am confirming that I am competent in the
required engineering aspects and that this statement of certification, if accepted, will be relied upon by
Council for the purposes of establishing compliance with the above Engineering Approval.
Signed:
Professional qual
(circle one):
CPEng / RPSurv
Date:
Member of (circle
relevant):
ACENZ / EngNZ / SSNZ
Registration
number:
Page 23 of 37
March 2024
RE 2.1.23 (V3)
Developer’s name and address:
All values are to be exclusive of GST
Category
Diam.
Material
Measure
Cost / Value
Council’s
Contribution
Stormwater
Stormwater Pipes*
Length (m)
Length (m)
Manholes / Chambers
No.
Inlet / Outlet
No.
Catchpits
No.
Pumpstations
No.
Treatment Devices
No.
Detention Tanks
No.
Ponds
No.
Lot Connections
No.
Subtotal:
Wastewater
Wastewater Pipes
Length (m)
Length (m)
Manholes / Chambers
No.
Outlets
No.
Valves
No.
Pumpstations
No.
Lot connections
No.
Subtotal:
Water Supply - Potable
Watermain
Length (m)
Length (m)
Hydrants
No.
Valves
No.
Pumpstations
No.
Manholes / Chambers
No.
Bores
No.
Intake Structures
Diam.
Subtotal:
Water Supply - Non Potable
Watermain
Length (m)
Hydrants
No.
Valves
No.
Pumpstations
No.
Manholes / Chambers
No.
Reservoirs
No.
Subtotal:
This information is certified as being true and correct
Name:
Company:
Signed:
Dated:
Position of signatory in relation to developer:
* Note: "Stormwater Pipes" to be vested as public are deemed public to the first joint or 1m inside the connection boundary whichever is the lesser.
For further clarification refer to "Stormwater Connections (inside the property)
Schedule of Land and Assets to Vest in Council
Sheet 1: Four waters
Notice for assets vested from a development at:
Site address:
Suburb:
Sub / Land use consent #:
Eng approval #:
Completion date:
Page 24 of 37
March 2024
RE 2.1.23 (V3)
Developer’s name and address
All values are to be exclusive of GST
Land to Vest
Land Use
Area (m
2
)
Cost / Value
Council’s Contribution
Roading
Recreation Reserve
Local Purpose Reserve
Other
Subtotal:
Category
Measure
Cost / Value
Council’s Contribution
Roading
Roading (must match RAMM sheet
entries)
Area (m
2
)
Footpaths
Area (m
2
)
Kerb & Channel
Length (m)
Street Lights
No.
Street Trees
No.
Traffic Signals
No.
Traffic Signs
No.
Bridges - vehicle
No.
Catchpits
No.
Retaining Walls
Item
Fences
Item
Noise Walls
Length (m)
Subtotal:
Parks
Bridges - Pedestrian
No.
Trees, Shrubs
No.
Boardwalks
Area (m
2
)
Planter Boxes
No.
Playgrounds
No.
Accessways/carparks
Area (m
2
)
BBQ
No.
Litterbin
No.
Picnic Tables
No.
Seats/benches
No.
Subtotal:
Other
Buildings
Item
This information is certified as being true and correct
Name:
Company:
Position of signatory in relation to developer:
Signed:
Dated:
Schedule of Land and Assets to Vest in Council
Sheet 2: Land, Roading and Parks
Notice for assets vested from a development at:
Site address:
Suburb:
Sub / Land Use Consent #:
Eng approval #:
Completion date:
Page 25 of 37
March 2024
RE 2.1.23 (V2d)
Stormwater
Asset name (from asbuilt)
Asset name (from GIS)
* please note Council may add
GIS references to this form if left
blank.
Asset type
(e.g. gravity pipe / manhole
/ outlet)
Size (mm)
Material
Quantity (see
note below)
Disposal type
(e.g. abandoned / removed)
Reason for disposal
(e.g. capacity, deterioration, re-
alignment)
Wastewater
Asset name (from asbuilt)
Asset name (from GIS)
* please note Council may add
GIS references to this form if left
blank.
Asset type
(e.g. gravity pipe / manhole
/ outlet)
Size (mm)
Material
Quantity (see
note below)
Disposal type
(e.g. abandoned / removed)
Reason for disposal
(e.g. capacity, deterioration, re-
alignment)
Water supply
Asset name (from asbuilt)
Asset name (from GIS)
* please note Council may add
GIS references to this form if left
blank.
Asset type
(e.g. pipe / manhole / outlet)
Size (mm)
Material
Quantity (see
note below)
Disposal type
(e.g. abandoned / removed)
Reason for disposal
(e.g. capacity, deterioration, re-
alignment)
Note
: Only the length to be abandoned is to be entered. If an entire section between
manholes, enter the length between (the outside) of each manhole. If it is a relaid
section of pipe then only that length that has been removed and replaced is to be
entered..
Schedule of Abandoned Assets
Sheet 1: Three Waters
Developer’s name and address:
Notice for assets abandoned from a development at:
Site address:
Suburb:
Sub / Land use consent #:
Eng approval #:
Completion date:
This information is certified as being true and correct
Name:
Company:
Position of signatory in relation to developer:
Signed:
Dated:
Page 26 of 37
March 2024
RE 2.1.23 (V2d)
Roading (affecting Cornerstone Drive and Elliot Rose Avenue)
Asset name (from asbuilt)
Asset name (from GIS)
* please note Council may add
GIS references to this form if left
blank.
Asset type
(e.g. footpath, carriageway,
streetlight)
Width
Material
Quantity (see
note below)
Disposal type
(e.g. abandoned / removed)
Reason for disposal
Kerb and channel
K & C
55m
removed
new intersections
footpaths
footpath
55m
new intersections
Parks
Asset name (from asbuilt)
Asset name (from GIS)
* please note Council may add
GIS references to this form if left
blank.
Asset type
Comments
Quantity (see
note below)
Disposal type
(e.g. abandoned / removed)
Reason for disposal
Other
Asset name (from asbuilt)
Asset name (from GIS)
* please note Council may add
GIS references to this form if left
blank.
Asset type
Comments
Quantity (see
note below)
Disposal type
(e.g. abandoned / removed)
Reason for disposal
Note: only the length to be abandoned is to be entered.
Schedule of Abandoned Assets
Sheet 2: Roading & other
Developer’s name and address:
Notice for assets abandoned from a development at:
Site address:
Suburb:
Sub / Land use consent #:
Eng approval #:
Completion date:
This information is certified as being true and correct
Name:
(Consultant)
Company:
Position of signatory in relation to developer:
Signed:
Dated:
7.69m 600mm Ø RCRRJ Class X
New Public SW @ 2.73%
New Precast Concrete
Wingwall
IL=1.56
1753865.18mE
5918574.59mN
New Public SWMH1
LL=3.89
1500mm Ø
1753872.20mE
5918579.28mN
New Public SWMH2
Scruffy Dome inlet
LL=4.34
1500mm Ø
1753879.65mE
5918646.47mN
New Public SWMH6
LL=7.00
1050mm Ø
1753856.19mE
5918621.37mN
New Public SWMH5
LL=6.50
1050mm Ø
1753877.27mE
5918629.16mN
New Public SWMH 4
LL=6.42
1050mm Ø
1753912.41mE
5918654.01mN
Extg SWMH A
LL=6.61
1050mm Ø
1753926.84mE
5918664.22mN
New Precast Concrete
Wingwall
IL=3.70
1753918.51mE
5918636.02mN
New Public SWMH3
LL=2.67
1050mm Ø
1753917.07mE
5918646.47mN
4.19
4.26
4.76
3.51
4.01
3.82
3.81
3.70
4.91
4.96
5.28
5.34
1.94
1.78
1.77
1.56
Northwest Street
15.34m 600mm Ø RCRRJ Class X
New Public SW @ 0.24%
20.97m 300mm Ø RCRRJ Class X
New Public SW @ 1.53%
41.54m 300mm Ø RCRRJ Class X
New Public SW @ 1.73%
16.18m 300mm Ø RCRRJ Class X
New Public SW @ 3.09%
7.36m 450mm Ø RCRRJ Class Z
Extg Public SW @ 2.58%
9.80m 450mm Ø RCRRJ Class X
Extg Public SW @ 1.12%
Top of Bund
RL = 3.83m
Top of Bund
RL = 3.81m
Top of Bund
RL = 3.76m
Base of Forebay
RL = 3.21m
Base of pond
RL = 3.32m
Base of Pond
RL = 3.36m
1
2
3
4.5
5.0
5.5
6.0
RL=4.64m - 1 in 100yr storage level
RL=4.47m - 1 in 10yr storage level
5
64
N
Base of Pond
RL = 3.26m
Easting Northing
1753928.97mE 5918633.57mN
1753914.00mE 5918631.18mN
1753908.95mE 5918627.65mN
1753898.00mE 5918620.85mN
1753894.46mE 5918618.12mN
1753886.58mE 5918612.77mN
1753876.72mE 5918605.36mN
1753875.85mE 5918600.70mN
1753878.98mE 5918593.80mN
1753886.90mE 5918596.87mN
1753893.89mE 5918599.38mN
1753904.01mE 5918604.84mN
1753910.96mE 5918609.49mN
1753923.82mE 5918619.56mN
1753927.07mE 5918624.47mN
1753926.54mE 5918629.75mN
1753918.95mE 5918628.08mN
1753914.98mE 5918622.00mN
1753903.96mE 5918614.98mN
1753897.69mE 5918610.59mN
1753888.72mE 5918604.95mN
1753882.20mE 5918601.79mN
POND COORDINATES (NZTM)
DESIGN POND VOLUMES
Dead water volume = 264m³
Water quality volume = 381m³
1 in 10 yr capacity = 169m³
1 in 100 yr capacity = 271m³
ASBUILT POND VOLUMES
Dead water volume = 268m³
Water quality volume = 390m³
1 in 10 yr capacity = 173m³
1 in 100 yr capacity = 277m³
Access Track
Northwest Street
4.5
5.0
5.5
6.0
N
SAMPLE POND ASBUILT PLAN
Northwest Street - ENG0000000
1 of 2
Rev2
Added bund levels
22/3/12
DLS
LOCATION PLAN
I certify that these as-built plans are an accurate record of works undertaken and that:
· The Coordinates (X, Y) are in terms of NZTM on NZGD(2000), and are within ±50mm.
· The Levels (Z) are in terms of the NZVD 2016/Auckland 1946 (MSL) LINZ datum
(DOSLI datum), and are within the following tolerances:
- For all pipe inverts & roadside channels to be within +/- 10mm (local circuit i.e
internal/relative consistency required only)
- For all other assets +/-20mm (e.g Manhole covers, Earthworks)
Name : ___________________________________________________
Signed : __________________________________________________
Registered Professional Surveyor/Licensed Cadastral Surveyor/
Certified Professional Engineering Surveyor
Registraion Number : ___________________ Date: _______________
Contact Number: ___________________________________________
Email: ____________________________________________________
Section 1 - Longsection
RL=4.64m - 1 in 100yr storage level
RL=4.47m - 1 in 10yr storage level
RL=4.34m - Water Quality Level
RL=3.84m - Dead Water Level
RL=3.26m - Base of Pond
600mm clay liner
RL=3.36m - Base of Pond
RL=3.32m - Base of Pond
RL=3.21m - Base of Pond
RL=3.76m - Top of bundRL=3.81m - Top of bund
RL=3.83m - Top of bund
Access track
Fence
7.23m 6.55m 10.4m 7.43m 12.46m 8.27m 6.84m
RL=4.64m - 1 in 100yr storage level
RL=4.47m - 1 in 10yr storage level
RL=4.34m - Water Quality Level
RL=3.84m - Dead Water Level
RL=3.36m - Base of Pond
600mm clay liner
Section 2 - cross section
Access track
Fence
16.23m
1
10
1
1.8
1
11.5
RL=4.64m - 1 in 100yr storage level
RL=4.47m - 1 in 10yr storage level
RL=4.34m - Water Quality Level
RL=3.84m - Dead Water Level
RL=3.32m - Base of Pond
600mm clay liner
Section 3 - cross section
Access track
Fence
15.91m
1
1.8
1
3
RL=4.64m - 1 in 100yr storage level
RL=4.47m - 1 in 10yr storage level
RL=4.34m - Water Quality Level
RL=3.84m - Dead Water Level
invert level=1.94m
invert level=1.78m
invert level=1.77m
invert level=1.56m
MHWS
400mm minimum
gabion rock
7.69m 600mm Ø RCRRJ Class X
New Public SW @ 2.73%
New Precast Concrete
Wingwall
IL=1.56
1753865.18mE
5918574.59mN
New Public SWMH1
LL=3.89
1500mm Ø
1753872.20mE
5918579.28mN
New Public SWMH2
Scruffy Dome inlet
LL=4.34
1500mm Ø
1753879.65mE
5918646.47mN
15.34m 600mm Ø RCRRJ Class X
New Public SW @ 0.24%
Section 4 - Outlet system
4.00m
Section 5 - Spillway cross section
RL=4.64m - 1 in 100yr storage level
RL=4.47m - 1 in 10yr storage level
600mm clay
liner
RL=4.30m - Spillway weir level
8.7m
12.91m OLFP @ 21% (1:4.75)
MHWS
Access track
Section 6 - Spillway longsection
600mm clay liner
RL=4.30m - Spillway weir level
12.91m
SAMPLE POND ASBUILT PLAN
Northwest Street - ENG0000000
2 of 2
Rev2
22/3/12
DLS
Added bund levels
Scale 1:250 @ A3
Scale 1:250 @ A3
Scale 1:250 @ A3
Scale 1:250 @ A3
Scale 1:125 @ A3
Scale 1:250 @ A3
I certify that these as-built plans are an accurate record of works undertaken and that:
· The Coordinates (X, Y) are in terms of NZTM on NZGD(2000), and are within ±50mm.
· The Levels (Z) are in terms of the NZVD 2016/Auckland 1946 (MSL) LINZ datum
(DOSLI datum), and are within the following tolerances:
- For all pipe inverts & roadside channels to be within +/- 10mm (local circuit i.e
internal/relative consistency required only)
- For all other assets +/-20mm (e.g Manhole covers, Earthworks)
Name : ___________________________________________________
Signed : __________________________________________________
Registered Professional Surveyor/Licensed Cadastral Surveyor/
Certified Professional Engineering Surveyor
Registraion Number : ___________________ Date: _______________
Contact Number: ___________________________________________
Email: ____________________________________________________
extg. SWMH
NS9099
LL=6.13
1753302.05mE
5915327.39mN
3.51
2.69
2.69
15.7m 1500mm Ø RCRRJ Class Z
Extg Public SW @ 5.22%
New Precast Concrete
Wingwall
IL=1.14
1753464.37mE
5915455.15mN
3.8m 1500mm Ø RCRRJ Class Z
Extg Public SW @ 5.22%
2.67
extg. SWMH
NS9098
LL=5.63
1753317.69mE
5915327.62mN
New SW Inlet
Scruffy Dome
2550mmØ
PWL overflow=2.58
1753446.68mE
5915446.06mN
1.41
1.30
1.28
4.0m 1050mm Ø RCRRJ Class X
New Public SW @ 5.22%
14.4m 1050mm Ø RCRRJ Class X
New Public SW @ 5.22%
New Precast
Concrete Wingwall
IL=2.67
1753321.64mE
5915329.73mN
New SWMH
LL=3.63
1753459.70mE
5915454.91mN
3.55
1
2
3
4
5
6
1.0
1.5
2.0
1.5
2.5
3.0
3.5
4.0
4.5
5.0
1.5
2.0
2.5
3.0
3.5
4.0
3.0
4.0
3.5
3.0
Top of bank
Top of bank
Top of bank
Top of bank
Easting Northing
Top of Bank
1753336.06mE 5915335.32mN
1753360.69mE 5915351.77mN
1753386.70mE 5915367.18mN
1753386.70mE 5915385.39mN
1753435.33mE 5915394.77mN
1753443.92mE 5915403.43mN
1753452.60mE 5915434.06mN
1753451.33mE 5915444.61mN
1753441.54mE 5915455.04mN
1753435.09mE 5915455.98mN
1753425.10mE 5915451.66mN
1753397.85mE 5915422.77mN
1753373.58mE 5915397.56mN
1753356.14mE 5915378.48mN
1753328.78mE 5915344.59mN
Forebay
1753328.18mE 5915334.38mN
1753360.93mE 5915357.92mN
1753355.55mE 5915367.51mN
1753326.46mE 5915336.33mN
Easting Northing
Bay 2
1753366.20mE 5915361.71mN
1753388.25mE 5915374.43mN
1753384.00mE 5915391.39mN
1753380.51mE 5915393.07mN
1753360.28mE 5915374.46mN
Bay 3
1753393.25mE 5915377.83mN
1753410.35mE 5915387.90mN
1753403.75mE 5915414.86mN
1753401.40mE 5915414.86mN
1753387.18mE 5915400.56mN
Bay 4
1753417.04mE 5915391.55mN
1753429.03mE 5915397.88mN
1753419.48mE 5915434.40mN
1753417.70mE 5915434.40mN
1753409.39mE 5915420.45mN
Bay 5
1753435.06mE 5915400.97mN
1753446.96mE 5915424.89mN
1753431.04mE 5915450.46mN
1753424.39mE 5915443.06mN
Wetland Coordinate Table
extg. SWMH
NS9099
LL=6.13
1753302.05mE
5915327.39mN
3.51
2.69
2.69
15.7m 1500mm Ø RCRRJ Class Z
Extg Public SW @ 5.22%
3.8m 1500mm Ø RCRRJ Class Z
Extg Public SW @ 5.22%
2.67
extg. SWMH
NS9098
LL=5.63
1753317.69mE
5915327.62mN
New Precast
Concrete Wingwall
IL=2.67
1753321.64mE
5915329.73mN
3.55
New Precast Concrete
Wingwall
IL=1.14
1753464.37mE
5915455.15mN
New SW Inlet
Scruffy Dome
2550mmØ
PWL overflow=2.58
1753446.68mE
5915446.06mN
1.41
1.30
1.28
4.0m 1050mm Ø RCRRJ Class X
New Public SW @ 5.22%
14.4m 1050mm Ø RCRRJ Class X
New Public SW @ 5.22%
New SWMH
LL=3.63
1753459.70mE
5915454.91mN
3.0
South East Lane
extg. SWMH
NS9099
LL=6.13
1753302.05mE
5915327.39mN
3.51
2.69
2.69
15.7m 1500mm Ø RCRRJ Class Z
Extg Public SW @ 5.22%
New Precast Concrete
Wingwall
IL=1.14
1753464.37mE
5915455.15mN
3.8m 1500mm Ø RCRRJ Class Z
Extg Public SW @ 5.22%
2.67
extg. SWMH
NS9098
LL=5.63
1753317.69mE
5915327.62mN
New SW Inlet
Scruffy Dome
2550mmØ
PWL overflow=2.58
1753446.68mE
5915446.06mN
1.41
1.30
1.28
4.0m 1050mm Ø RCRRJ Class X
New Public SW @ 5.22%
14.4m 1050mm Ø RCRRJ Class X
New Public SW @ 5.22%
New Precast
Concrete Wingwall
IL=2.67
1753321.64mE
5915329.73mN
New SWMH
LL=3.63
1753459.70mE
5915454.91mN
3.55
1
2
3
4
5
6
1.0
1.5
2.0
1.5
2.5
3.0
3.5
4.0
4.5
5.0
1.5
2.0
2.5
3.0
3.5
4.0
3.0
4.0
3.5
3.0
Top of bank
Top of bank
Top of bank
Top of bank
1.83
SAMPLE WETLAND ASBUILT
South East Lane - ENG0000000
1 of 2
Rev1
Amended coordinate system - NZTM
22/3/12
DLS
N
ROCK ARMOUR
Grass lined Overflow
Channel
400mm minimum RIP RAP
on 150mm GAP 65 bedding
400mm minimum RIP RAP
on 150mm GAP 65 bedding
ZOOM A
ZOOM B
ZOOM B
ZOOM A
POND PLANTING SCHEDULE
AQUATIC AREA
DEEP ZONE 0.5-1m
Juncus Palladus
Baumea Articulata
SHALLOW ZONE 0-0.5m
Eleocharis Sphacelata
Juncus Paladus
LOWER BANK ZONE
Carex Secta / Carex Virgata
Apadasmia Similis
MID BANK ZONE
Cortaceria Fulvida
Phormium Cookianum
UPPER BANK ZONE
Apodosmia Similis
Phormium Cookianum
Phormium Tenax
Cordyline Australis
LOCATION PLAN
I certify that these as-built plans are an accurate record of works undertaken and that:
· The Coordinates (X, Y) are in terms of NZTM on NZGD(2000), and are within ±50mm.
· The Levels (Z) are in terms of the NZVD 2016/Auckland 1946 (MSL) LINZ datum
(DOSLI datum), and are within the following tolerances:
- For all pipe inverts & roadside channels to be within +/- 10mm (local circuit i.e
internal/relative consistency required only)
- For all other assets +/-20mm (e.g Manhole covers, Earthworks)
Name : ___________________________________________________
Signed : __________________________________________________
Registered Professional Surveyor/Licensed Cadastral Surveyor/
Certified Professional Engineering Surveyor
Registraion Number : ___________________ Date: _______________
Contact Number: ___________________________________________
Email: ____________________________________________________
Section 1 - Bay 1 cross section Scale 1H:2V
Peak Water Level, PWL = 2.58m
600mm clay liner
24.36m
5.62m
1
1.5
1
3.75
1
3.25
1
1.25
Normal Water Level, NWL = 1.83m
1.00m
1.03m
0.18m
0.85m
1.02m
0.21m
0.81m
0.88m
1.04m
0.16m
1.56m
0.92m
0.64m
Section 5 - Typical longsection
Scale 1H:5V
Peak Water Level, PWL = 2.58m
600mm clay liner
400mm minimum
gabion rock riprap
Aquatic planting area
1050mm dia. RCRRJ Class X
2550mm dia. Scruffy Dome inlet
on pre-cast concrete riser
Aquatic planting area
Aquatic planting area
Aquatic planting area
5.56m17.26m 27.81m
31.28m
6.04m 20.16m 7.95m 14.26m 8.17m 30.03m
Normal Water Level, NWL = 1.83m
Section 6 - Coastal bank profile Scale 1H:2V
Peak Water Level, PWL = 2.58m
600mm clay liner
1
2.25
Section 4 - Inland bank profile Scale 1H:2V
Peak Water Level, PWL = 2.58m
600mm clay liner
1
6
Normal Water Level, NWL = 1.83m
Section 2 - Bay 2 cross section Scale 1H:2V
Peak Water Level, PWL = 2.58m
600mm clay liner
31.43m
16.51m
1
5
1
1.5
1
8
Normal Water Level, NWL = 1.83m
Section 3 - Shallow planted zone Scale 1H:2V
Peak Water Level, PWL = 2.58m
600mm clay liner
23.4m
12.65m
1
1.4
1
5
Normal Water Level, NWL = 1.83m
SAMPLE WETLAND ASBUILT - Longsection
South East Lane - ENG0000000
2 of 2
Rev1
Amended coordinate system - NZTM
22/3/12
DLS
Scale 1:250 @ A3
Scale 1:250 @ A3
Scale 1:250 @ A3
Scale 1:250 @ A3
Scale 1:250 @ A3
Scale 1:500 @ A3
I certify that these as-built plans are an accurate record of works undertaken and that:
· The Coordinates (X, Y) are in terms of NZTM on NZGD(2000), and are within ±50mm.
· The Levels (Z) are in terms of the NZVD 2016/Auckland 1946 (MSL) LINZ datum
(DOSLI datum), and are within the following tolerances:
- For all pipe inverts & roadside channels to be within +/- 10mm (local circuit i.e
internal/relative consistency required only)
- For all other assets +/-20mm (e.g Manhole covers, Earthworks)
Name : ___________________________________________________
Signed : __________________________________________________
Registered Professional Surveyor/Licensed Cadastral Surveyor/
Certified Professional Engineering Surveyor
Registraion Number : ___________________ Date: _______________
Contact Number: ___________________________________________
Email: ____________________________________________________
Engineering Approval Completion Certificate
Issued By: Auckland Council Regulatory Engineering
Project Address:
Street number, name
Suburb
City
Post code
Applicant:
(Name/Company)
(Address)
Auckland
Note: A final Engineering Approval Completion Certificate (EACC) issued in respect to all the
engineering works covered by the above Approval.
The Statement of Certification has been signed and dated by:
(CPEng /Registered Surveyor)., Date
The As-built plan has been signed and dated by: (Surveyor)
Auckland Council Regulatory Engineering is satisfied upon reasonable grounds that: these
works, certified by Name have met the requirements of the Engineering Approval.
Signed for and on behalf of Council on this day: < DD/MM/YY >
……………………………………
<Name>
Team Leader
Regulatory Engineering
Auckland Council
Engineering Approval Completion Certificate (EACC) Regulatory Engineering
Page 32 of 32 March 2024 RE 2.1.23 (V2d)
Project:
(Project type)
Consent Number: ENG600XXXXX Release Date: D/M/Y
This Engineering Approval Completion Certificate is granted subject to the following conditions:
That 24-hour access to public infrastructure on private land be provided to Auckland
Council, Watercare and its representatives in accordance with the Local Government Act
2004.
That a post-construction audit may be carried out of these works.
That subsequent to this audit, if the works associated with this consent are found to be